A replacement tube bundle was required. The project was managed by the client with Five-D carrying out the engineering and design and local fabricator doing he manufacture.
Five-Ds scope was to design and engineer the tube bundle to meet the latest code requirements and to fit the existing shell and channel head.
- Design to ASME VIII Div. 1 / TEMA
- Obtain Design Verification