Super Duplex Piping Upgrade
SERVICES LINES
Mechanical Engineering
Design Drafting
INDUSTRY SECTOR
PetraEnergy
Infrastructure
Renewables
Geothermal
PROJECT SUMMARY
Five-D was engaged to deliver the Tauhara Super Duplex Piping Upgrade. A schedule-driven project that required a fast and accurate turnaround to enable fabrication and field installation. Leveraging high-resolution 3D scan and survey data provided by BTW, the Five-D team developed precise 3D models and 26 fabrication-ready isometric drawings, detailing over 45 brownfield tie-in locations in less than 4 weeks.
The accuracy and clarity of the spool dimensions and flange alignments enabled shop fabrication and precision drop-in installation of the new spools, thereby reducing both installation time and downtime on a critical, time- and cost-sensitive project.
SCOPE
Interpreting BTW cold point cloud survey / model and creating a 3D model new Super Duplex piping spools
Produce isometrics for fabrication of new spools – including accurate detailing of flange alignment and rotation on isometrics
CHALLENGES'
Schedule:
Originally agreed 6-8 weeks with client, but delivered in less than 4 to meet shutdown fabrication schedule.
Work packs are broken across three separate fabrication/install service providers, requiring an immediate start.
Accuracy:
Significant spool distortion and flange misalignment/rotation on individual spools meant pin point accuracy and careful checking was required.
OUTCOME
Delivery of 3D models and Fabrication isometrics significantly ahead of schedule, below budget and to a very high quality.